Virginia Contractor Class A or Class B General Exam Version 3
Practice exam for Contractor License Exams under Contractor Certification Exams (Licensing Exams). 5 sample questions.
Sample Questions
You're viewing a limited preview. Log in and subscribe to access all questions.
Log InExam Questions
Question 1
A construction project may not require an inspection at the discretion of the inspecting authority if its cost is less than what MAXIMUM amount?
Correct Answer: A
Rationale: Virginia regulations allow local building officials to waive inspections for minor work valued at $2,500 or less. Projects exceeding $2,500 generally require permits and inspections unless specifically exempted.
Rationale: Virginia regulations allow local building officials to waive inspections for minor work valued at $2,500 or less. Projects exceeding $2,500 generally require permits and inspections unless specifically exempted.
Question 2
Which option is NOT a requirement for the designated employee of a corporation?
Correct Answer: D
Rationale: The designated employee (or responsible management) must be at least 18, work full-time for the licensee, and pass the required exam. There is no requirement that the designated employee personally hold a controlling financial interest in the company.
Rationale: The designated employee (or responsible management) must be at least 18, work full-time for the licensee, and pass the required exam. There is no requirement that the designated employee personally hold a controlling financial interest in the company.
Question 3
Modifications to a contract effecting cost materials, work scope, or estimated completion date shall
Correct Answer: B
Rationale: Virginia DPOR regulations require that any change affecting price, materials, scope, or completion date must be in writing and signed by all parties before the work is performed.
Rationale: Virginia DPOR regulations require that any change affecting price, materials, scope, or completion date must be in writing and signed by all parties before the work is performed.
Question 4
The Contractor Transaction Recovery Fund was created to provide a remedy to damaged
Correct Answer: B
Rationale: The Virginia Contractor Transaction Recovery Fund exists to compensate homeowners (residential owners) who suffer financial loss due to improper or dishonest conduct by licensed contractors.
Rationale: The Virginia Contractor Transaction Recovery Fund exists to compensate homeowners (residential owners) who suffer financial loss due to improper or dishonest conduct by licensed contractors.
Question 5
The designated employee MUST work a MINIMUM of how many hours per week for the licensed contracting business?
Correct Answer: B
Rationale: The designated employee or member of responsible management must devote full time (defined as at least 30 hours per week) to the contracting business.
Rationale: The designated employee or member of responsible management must devote full time (defined as at least 30 hours per week) to the contracting business.